Baratang Island in September
Andaman & Nicobar Islands, India
Baratang in September is the slow tail of monsoon and the day-trip is mostly still impossible. Rainfall drops to 290-340mm, mostly first half. The ATR has 2-3 unrepaired landslide stretches that the Andaman Public Works Department clears through October. Creek boat operators at Nilambur are mostly still shut - the first ones return mid-October. Port Blair tour operators do not start selling Baratang packages until October 20-25, and even then on a tentative basis. The limestone cave back chamber is still flooded; the mud volcano road is still partly broken. Wait six weeks for November's clean opening.
Why September scores 4.0/10
Weather
Late monsoon. 320mm rain. ATR repairs ongoing. Creek boats not yet running. Operators shut.
What to do in Baratang Island this September
- 1Wait for October reopening
- 2Plan Port Blair base-only itinerary
Who should go
- ✓Travelers with basic fitness
- ✓Late-monsoon recovery seekers
Who should think twice
- ✗Those with mobility issues
- ✗Activity-focused planners
All 12 Months
| Month | Score | Note |
|---|---|---|
| January | 10.0/10 | Peak. 22-29C, dry. Convoy reliable, mud volcano + caves running. 4am Port Blair start required. |
| February | 10.0/10 | Driest, calmest. 23-30C. Cave boat ride glass-flat. Convoy on schedule. Best month for Baratang. |
| March | 8.0/10 | Late peak. 25-31C. Cave dry, mud volcano stable, creek boat calm. Day-trip prices 20% off Feb. |
| April | 8.0/10 | Hot 27-32C. Cave still dry, creek boat calm. ATR convoy on schedule. Big heat at the mud volcano. |
| May | 6.0/10 | Pre-monsoon. First half OK. After May 18 squalls cancel creek boats and ATR closes for landslides. |
| June | 2.0/10 | Monsoon. ATR closes for landslides routinely. Creek boats off, cave access flooded. Skip. |
| July | 2.0/10 | Peak monsoon. ATR closed routinely. All headline activities off. Skip. |
| August | 2.0/10 | Monsoon continues. 460mm rain. ATR broken, boats off, cave flooded. Skip entirely. |
| Septemberviewing | 4.0/10 | Late monsoon. 320mm rain. ATR repairs ongoing. Creek boats not yet running. Operators shut. |
| October | 6.0/10 | Recovery. 180mm rain. ATR reopens mid-month, creek boats restart late. Last week works. |
| November | 8.0/10 | Properly open. 60mm rain, 23-30C. Convoy on schedule, creek boats daily, cave dry, mud volcano firm. |
| December | 10.0/10 | Peak. 22-29C, dry. Convoy reliable, cave dry, creek glass-flat. Christmas-NY 40% premium. |
What to pack for September
- ▸Indoor activity list
- ▸Port Blair hotel confirmation
ठहरने की बुकिंग के लिए तैयार हैं?
हम बुकिंग से पहले आते हैं, उसके साथ नहीं — नीचे दिए प्लेटफ़ॉर्म पर दाम की तुलना करें।
किसी भी जगह, ठहरने या ऑपरेटर को दिखाने के लिए हम पैसे नहीं लेते। यहाँ दिए किसी लिंक से बुकिंग करने पर हमें थोड़ा कमीशन मिल सकता है, आप पर कोई अतिरिक्त खर्च नहीं। इससे हमारे स्कोर या सुझावों पर कभी असर नहीं पड़ता। संपादकीय नीति
अगले Baratang Island के लिए तैयार रहें
रविवार को एक ईमेल — कौन सी जगह अगले हफ़्ते जाने लायक है। साथ ही जो जगहें आप सहेजें, उनके पीक से तीन हफ़्ते पहले हेड्स-अप। बिना स्पैम।
Free. No sponsored picks. Unsubscribe in one click.